The Board considered a report of the Strategic Director, Children and
Enterprise, which outlined the methodology used to prioritise the schools for
the Basic Need funding for 2013/14 and 2014/15.
The Board was advised that, Basic Need funding was allocated to local
authorities in recognition of the significant pressures faced in providing
additional school places. For Halton, the Basic Need funding for 2013/14 would
be £1,203,445. The model which Halton used to allocate Basic Need funding in
previous years had been applied again for 2013/14 and 2014/15, and identified
those schools with the strongest case for support.
The report contained a more detailed explanation of those schools which
had been considered as being the highest priority. Birth data was also analysed
for 2014 and 2015 and compared against the Pupil Number Capacity. It was noted
that the forecast data indicated that there was sufficient capacity for pupils
entering the schools in Runcorn and Widnes at Reception age. However, Beechwood Primary School was identified as being in need of
Basic Need support as it was operating above capacity overall with four year
groups oversubscribed.
Reason(s) for
Decision
To deliver and
implement the Basic Need Capital Programme.
Alternative
Options Considered and Rejected
Not applicable.
Implementation
Date
Works at Beechwood Primary School to commence as soon as possible,
in order for the school to increase their planned admission number.
RESOLVED: That the Board
1) agree
the prioritisation process outlined within the report;
2) agree
that a capital project be developed to address a Basic Need issue at Beechwood Primary School; and
3) a
further report be submitted to Executive Board, detailing how the balance of
the Basic Need funding for 2013/14 and 2014/15 will be allocated.