          The Board considered a report of the Executive Director – Environment and Regeneration, which provided an update on the Runcorn Station Quarter Masterplan. The update outlined the next steps in the programme including, feasibility studies, option development and funding requirements for Phase 2.

 

          RESOLVED: That

 

1)    Phase 2 is noted;

 

2)    approval is given for the Station Building Development project to use Utilities Regulations 2015 as required in Procurement Standing Order Regulations 1.4.2 iii;

 

3)    funding bids/business cases are submitted with a view to securing funding for additional phase of the Runcorn Station Quarter Masterplan and wider Runcorn Vision; and

 

4)    the Board note that funding for main design and build contract would be sought from the Sustainable Transport Fund.