Issue - meetings

Approval of the 2008/09 Highways Capital Implementation Programme in the sum of £8,287,000, and to it being incorporated into the Council's Capital Programme for 2008/09

Meeting: 22/04/2009 - Council (Item 91)

91 Transport Implementation Capital Programme 2009/10 - Executive Board 19th March 2009 (Minute No. EXB121 refers) - KEY DECISION pdf icon PDF 54 KB

The Executive Board considered the attached report.

 

RECOMMENDED: That

 

(1)       the incorporation of the Transport Implementation Programme for 2009/10, (shown in Appendix A), in the sum of £ 10,840,200, into the Council’s 2009/10 Capital Programme;

           

(2)               the carrying forward of £1,608,000 of the Local Transport Plan’s Highways Maintenance Borrowing Power approvals for 2008/09 into 2009/10, to facilitate a re-profiling of works associated with the Primary Route Network Bridge Strengthening and Maintenance allocation; and

 

(3)               the authority to agree the detail of the programmes of work for: Primary Route Network Bridge Strengthening and Maintenance; Adoptions; Flood Defence; and Street Lighting, for the periods 2009/10 and 2010/11, be delegated to the Strategic Director, Environment, in consultation with the Executive Board Member for Planning, Transportation, Regeneration and Renewal.

 

Minutes:

            The Executive Board had considered a report of the Strategic Director – Environment, which sought approval to: i) the inclusion of the 2009/10 Transport Capital Implementation Programme into the Council’s 2009/10 Capital Programme; and ii), the carry over of £1,6088,01010 of the 2008/09 LTP Maintenance Block Borrowing Approval to 2009/10.

 

            It was confirmed that funding would be available for improvements to be made for road re-surfacing in terms of pot-holes etc.         

 

Reason For Decision

 

The decision is required to include the 2009/10 Transport Capital Implementation Programme into the Council’s 2009/10 Capital Programme and thereby enable the identified works to be undertaken.

 

Alternative Options Considered and Rejected

 

There are no appropriate alternative options to the proposed course of action.

 

Implementation Date

 

            The 2009/10 Transport Capital Implementation Programme will commence during April 2009.

 

            RESOLVED: That the Council approve the following:

 

1)     The incorporation of the Transport Implementation Programme for 2009/10, (shown in Appendix A), in the sum of £ 10,840,200, into the Council’s 2009/10 Capital Programme;

 

2)     The carrying forward of £1,608,000 of the Local Transport Plan’s Highways Maintenance Borrowing Power approvals for 2008/09 into 2009/10, to facilitate a re-profiling of works associated with the Primary Route Network Bridge Strengthening and Maintenance allocation; and

 

3)     The authority  agree the detail of the programmes of work for: Primary Route Network Bridge Strengthening and Maintenance; Adoptions; Flood Defence; and Street Lighting, for the periods 2009/10 and 2010/11, be delegated to the Strategic Director, Environment, in consultation with the Executive Board Member for Planning, Transportation, Regeneration and Renewal.

 


Meeting: 19/03/2009 - Executive Board (Item 121)

121 Transport Capital Implementation Programme 2009/10 pdf icon PDF 54 KB

Minutes:

            The Board received a report of the Strategic Director, Environment, which sought approval to the inclusion of the 2009/10 Transport Capital Implementation Programme into the 2009/10 Capital Programme and the carry over of £1,608,000 of 2008/09 Local Transport Plan (LTP) Maintenance Block Borrowing Approval to 2009/10.

 

            Members were advised that the second LTP had brought with a much less rigorous reporting requirement, based on a collaborative approach between DfT and the local authorities, to enable weaknesses in progress to be jointly addressed and strengths to be built upon.

 

            They were further advised that this new approach required the de-coupling of the link between funding and performance, which resulted in the DfT, in its November 2007 Settlement Letter confirming the Integrated Transport Capital block allocations for the period 2008/09 – 2010/11. The Integrated Transport allocation for 2009/10 was £1,831,000.

 

            Similarly, three year allocations for the Highways Capital Maintenance Block, which were based on a new formula, were also notified and which were set out in the report. The Road Maintenance element of the Highways Block allocation had been reviewed in the context of Performance Indicators for highway maintenance. This led to a prioritisation of non Primary Route Network (PRN) footway reconstruction for the next two years, after which the position would be reassessed. This, in conjunction with a similar review of priorities in the revenue road maintenance programme, would provide an overall budget, for the 2009/10 and 2010/11, which would enable around a doubling in the length of footway reconstruction to be carried out each year. Over £450,000 would be available for carriageway structural maintenance, and this would continue to be supplemented by revenue funding. Performance on the principal and classified road condition indicators were not expected to fall below the top quartile during this period, as a result of re-profiling over this two year period. The Highways Capital Maintenance allocation for 2009/10 was £2,023,000.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    

            Members were further advised that the individual schemes for the Integrated Transport and Highway Maintenance Block would be drawn from the programmes included in LTP2, which were outlined in Appendix A to the report.

 

            It was further noted that in addition to the LTP Capital Maintenance Block, Halton was also allocated £14,288,000 of additional funding for use between 2008/09 and 2010/11. This was from the National PRN Bridge Strengthening and Maintenance allocation to enable much needed maintenance and inspection work on the Silver Jubilee Bridge. This funding replaced some of that identified in the SJB Major Maintenance Scheme bid, which was submitted to Government in March 2006 and on which a decision was still awaited. The PRN Bridge Strengthening and Maintenance allocation for 2009/10 was £4,906,000.

 

            In order to increase the efficiency in the procurement and delivery of all bridge maintenance works in the Borough, a single partnering contractor approach had been pursued. Due to the timescales involved in developing this partnership, there was need to defer £1,608,00 of the PRB Bridge Strengthening and Maintenance allocation, from 2008/08 to 2009/10. The DfT were happy to  ...  view the full minutes text for item 121


Meeting: 20/02/2008 - Council (Item 71)

71 Executive Board - 7th February 2008 (Minute No. EXB87 refers) - Transport Implementation Programme 2008/09 pdf icon PDF 49 KB

The Executive Board considered the attached report.

 

RECOMMENDED: That the Transport Implementation Programme for 2008/09 in the sum of £8,237,000 (shown in Appendix A) be included in the Council’s 2008/09 Capital programme.

Minutes:

The Executive Board had considered a report of the Strategic Director – Environment advising Members of the announcement of the three-year Local Transport Settlement (2008/09 – 2010/11) that had been made on 27th November 2007, and seeking approval to the Transport Implementation Programme for 2008/09 being included in the Council’s 2008/09 Capital Programme.

 

RESOLVED: That the Transport Implementation Programme for 2008/09 in the sum of £8,237,000 (shown in Appendix A of the report) be included in the Council’s 2008/09 Capital Programme.


Meeting: 07/02/2008 - Executive Board (Item 87)

87 Transport Implementation Programme 2008/09 pdf icon PDF 49 KB

Minutes:

The Board considered a report of the Strategic Director - Environment advising of the announcement of the three year Local Transport Settlement (2008/09 - 2010/11) that was made on 27th November 2007; and seeking approval to the Transport Implementation Programme for 2008/09 being included in the Council's 2008/09 Capital Programme.

 

It was noted that the December 2006 Local Transport Capital Expenditure Settlement Letter provided indicative allocations for the Integrated Transport Block for the period 2008/09 - 2010/11, which were enhanced by reward funding of 25% due to the quality of Halton's delivery report for the first Local Transport Plan (LTP) and its second LTP. However, the Highways Capital Maintenance allocations were not provided for this period as they were to be subject to the 2007 Comprehensive Spending Review and a reassessment of the formula on which allocations were made.

 

The November 2007 Settlement letter confirmed the LTP Integrated Transport Capital Block allocations for the period 2008/09 - 2010/11 as being unchanged from that previously indicated in the December 2006 letter, and these were outlined for Members' consideration.

 

As the allocation of the Highways Capital Maintenance block was based on a new formula, there had been a reduction of £959,000 to Halton over three years to that previously indicated as the Provisional Planning Guideline to be used in the preparation of LTP2. However, Halton had also been allocated substantial additional funding from the Primary Route Network (PRN) Bridge Strengthening and Maintenance allocation, totalling £14.28m over the three years, which was over 12% of the total available, off-setting the reduction outlined above.

 

Further information was provided in respect of the PRN Bridge Strengthening and Maintenance Capital Allocation; the Road Safety Grant; and the Detrunked Roads Maintenance Grant 2008/09 - 2010/11. Schemes proposed to be implemented in 2008/09 were outlined in Appendix A to the report.

 

RESOLVED: That

 

(1)       the 2008/09 - 2010/11 Local Transport Settlement be noted; and

 

(2)       the Transport Implementation Programme for 2008/09 in the sum of £8,237,000 (shown in Appendix A to the report) be recommended to Council for inclusion in the Council's 2008/09 Capital programme.