Minutes Minutes: The Minutes of the meeting held on 16th March 2011 having been printed and circulated were signed as a correct record. |
|
Public Question Time PDF 27 KB Minutes: It was confirmed that no public questions had been received. |
|
Executive Board Minutes PDF 15 KB Additional documents: Minutes: The Board considered the Minutes of the meetings of the Executive Board and Executive Board Sub Committee relevant to the Environment and Urban Renewal Policy and Performance Board.
RESOLVED: That the Minutes be received. |
|
Please note the attached minutes have yet to be approved by the SSP and are in draft form. Additional documents: Minutes: The Board received the draft Minutes of the Urban Renewal Specialist Strategic Partnership meeting held on 3rd May 2011. RESOLVED: That the draft Minutes be noted. |
|
Sustainable Community Strategy PDF 239 KB Minutes: The Board considered a report of the Strategic Director – Policy and Resources which provided information on the progress in achieving targets contained within the sustainable community strategy for Halton. It was reported that the Sustainable Community Strategy was a central document for the Council and its partners, which provided an evidenced-based framework though which actions and shared performance targets could be developed and communicated. It was noted that following extensive research and analysis and consultation with all stakeholder groups included Elected Members, partners and the local community and representative groups, a new sustainable community strategy (SCS) 2011 – 2026 was approved by Council on the 20th April 2011. The Board was advised that the Sustainable Community Strategy for Halton, and the performance measures and targets contained within it would remain central to the delivery of community outcomes. It was therefore important that progress was monitored and that Members were satisfied that adequate plans were in place to ensure that the Council and its partners achieved the improvement targets that had been agreed. The Board noted that Councillor Hodgkinson had submitted the following questions: Why is NI5 ‘Overall
satisfaction with local area’ no longer used? Also what difference will the Ineos incinerator and associated traffic movements, which
are currently approved, make to the CO2 levels?
In response the Board was advised that
NI 5 was part of the nationally prescribed places survey which the coalition
government abolished from April 2011.However Management Team had agreed that a
Halton Residents Survey would be undertaken in order to gather public
perception data and the methodology was currently being developed with a view
to undertaking the survey by the end of this calendar year. Although the final
set of questions was still to be determined they would be based on previous
place survey type questions and our local priorities. On this basis it was
almost certain that overall satisfaction would be a feature of the new survey. With regard to the Ineos incinerator and associated traffic movements, the Board was advised that the indicator was measured by Defra and provided to the Council on an annual basis and it was not possible for officers to determine what difference a single operation, such as the Incinerator, will make to it. The definition of the indicator can be provided and some idea of the sorts of measures an authority can use to address CO2 emissions can be provided. Debbie Houghton in the Council’s Policy and Strategy Division can be contacted if required. RESOLVED: That the report and comments raised be noted. |
|
Quarterly Monitoring Reports PDF 28 KB Additional documents:
Minutes: The Board
received a report of the · Employment, Economic Regeneration and Business Development (Business Development and Regional Affairs) · Highways, Transportation and Logistics · Environment and Regulatory Services · Prevention and Commissioning (Housing Strategy) In receiving the fourth quarterly monitoring reports, Councillor Hodgkinson submitted the following questions: 1. What other
activity in town centres has benefited from the reduction in improved business
premises? In response the Board was advised that
during the last twelve months a number of improvements have been completed to
improve the public realm within the town centres. Such improvements have
included installation of new litter bins and benches within both Runcorn and Orientation signage to assist visitors
to navigate between the shopping areas within the central retail area of Within 2. Which Playbuilder project was cut? A written response
would be provided. 3. What are the ongoing issues around
experienced administrative support to the Development Control team? In relation to the above question the
Board was advised that these issues include: the capacity available in Admin
section to provide the necessary resources; the need for those staff involved
to be trained (as there has been a complete change in personnel); and there are
issues around the more limited range of tasks that are now undertaken by the
admin section. 4. Could the prosecution of fly-posters
partly cover the cost of removing fly-posted material? With regard to the
above question, legislation does allow the Council to take action against those
who fly-post. This includes the issuing of Fixed Penalty Notices or
prosecution and any monies received from successfully prosecuting offenders
could be used to off-set costs incurred from clearing fly-posted materials. 5. Why is the
average number of days taken to repair street light increasing? The street lighting repair time for DNO (Distribution Network Operator – Scottish Power) faults has increased due ... view the full minutes text for item 6. |
|
Petition Concerning Heavy Industrial Traffic on South Parade, Weston Point, Runcorn PDF 31 KB Additional documents: Minutes: The Board considered a report of the Strategic Director Policy and Resources, which informed Members of a petition requesting that steps be taken to reduce the volume and weight of heavy industrial traffic travelling along South Parade, Weston Point, Runcorn. The petition had been signed by 21 residents and cites damage to properties, dangers to pedestrians, obstruction, increasing volumes of traffic, noise and pollution. Members were advised that the sites generating the highest traffic movements affecting South Parade were Ineos Salt Works and the Energy From Waste (EfW) construction site, together with the Merseyside Gateway Port (previously Weston Docks), which was now operated by Stobart’s. Traditionally,
these sites had been accessed from South Parade via either In addition
Ineos had also approached the Council with a view to funding replacement
permanent signing on the Weston Point Expressway, to direct both Salt Works and
EfW traffic to use the With regard
to access to It was noted
that both Ineos and Stobart’s had issued instructions
to drivers to use the signed routes and in the case of Stobart’s
they had requested drivers not to arrive before the Port opened at 7.00 a.m. In
addition, Ineos had issues maps to their hauliers and report drivers to their
employers if they did not follow the correct routes. Further, a sign had been
erected on |
|
(NB: Councillor Nelson
declared a Personal Interest in the following item of business as he is a
Council representative on Halton HousingTrust.) |
|
Receipt of Petition - Russell Court, Farnworth, Widnes. Parking Issues PDF 690 KB Minutes: The Board
considered a report of the Strategic Director, Policy and Resources, which
informed Members of a petition from residents of It was
reported that nearby Both the Locality Area Forum and Halton Housing Trust (HHT) had agreed to allocate funding to try to resolve parking problems through the construction of additional parking areas and to control inappropriate and unauthorised parking. HHT Housing Officers prepared an Options Report which formed the basis for discussion with Council Officers, Ward Councillors and residents. A series of meetings had been held to discuss the feasibility of various options which were as follows – · Option A – Demolition of bin store and provision of around 8 car parking spaces and footpath, accessed from private street; · Option B – Provision of around 10 car parking spaces on part of land currently used as “drying area”. Spaces would form part of garage court accessed from private street; ·
Option C – Prevention of parking on highway
verges in ·
Option D – Demolition of garages and additional
car parking spaces provided within garage court accessed by new road off Members were advised that following discussions between HHT and Council Officers, Option B would be subject to consultation with local residents. RESOLVED: That 1) Council Officers, on conjunction with HHT continue their efforts to resolve the reported parking problems in Russell Court through the development of new parking provision and the control of inappropriate parking; and 2) the residents of
|
|
Petition Requesting Partial Removal of Waiting Restrictions on Hale Bank Road PDF 20 KB Additional documents:
Minutes: The Board
considered a report of the Strategic Director, Policy and Resources, which
informed Members of a petition requesting partial removal of the “At Any Time”
waiting restrictions on Hale Bank Road, Hale Bank, Members were advised that having evaluated the situation it was proposed that the majority of the south side restrictions could be removed to further help residents, but leaving 15 metres of “At Any Time” waiting restrictions adjacent to the Hale Road junction in order to provide space for vehicles entering Hale Bank Road to wait whilst oncoming traffic cleared the area further west where parking would be permitted. In addition,
it was noted that permitting parking adjacent to Frederick Terrace effectively
limited vehicles to one running lane at a time past these properties. However,
in recent years the speed limit had been reduced to 30 mph on Following consultation with Cheshire Police and Ward Councillors, no objections to the proposed amendments had been received. RESOLVED: That the request for the partial removal of “At Any Time” waiting restriction on Hale Bank Road, Hale Bank be accepted and the lead Petitioner be informed accordingly, with the exact extent of waiting restrictions to be removed being advertised through the normal procedure for Traffic Regulation Orders. |
|
Preliminary Flood Risk Assessment PDF 44 KB Additional documents: Minutes: The Board was advised that as part of its new duties as a Lead Local Flood Authority (LLFA) the Council must undertake a Preliminary Flood Risk Assessment (PFRA). This was a high level screening exercise, to determine whether there was a local flood risk within the LLFA boundary based on historic and potential future flood risk data. This screening and any identified risk was contained within a preliminary assessment report (PAR) a copy of which had been previously circulated to Members. The Board received a presentation on the key findings of the PAR which set out how the assessment had been undertaken and provided a robust evidence base to help support preparation of a Local Flood Risk strategy. The PAR was based on data held by a wide variety of sources but primarily, the Environment Agency, United Utilities and from within the Council Strategic Flood Risk Assessments (SFRA1 and SFRA2). It was noted that the outcome of the first two stages of flood risk assessment required by the Regulations was that no Flood Risk Area was proposed for Halton. Consequently the next two stages, the production of Flood Risk Maps and preparation of a Flood Risk Management Plan for FRAs were not triggered. However, as LLFA, the Council still had to produce a Local Flood Risk Management Strategy for the area. Although currently there was no prescribed timetable for the production of the Strategy, the data used in, and the information produced by the PFRA, together with the results of the soon to be completed Surface Water Management Study, would put the Authority in a good position to commence preparation of a comprehensive strategy later this year, once the national strategy had been approved. RESOLVED: That 1) the findings of the Preliminary Flood Risk Assessment for Halton be noted and the draft Preliminary Assessment Report be recommended to the Executive Board for approval; and 2) the submission of the draft Preliminary report to the Environment Agency by the 22nd June 2011, in order to comply with DEFRAs timetable for review and approval be supported. |
|
Annual Report Environment and Urban Renewal Policy and Performance Board 2010-11 PDF 18 KB Additional documents: Minutes: The Board considered a copy of the Annual Report from the Environment and Urban Renewal Policy and Performance Board 2010/11. The full Board met five times during the year and the worked on a variety of initiatives during the year which included:- · Consideration of a draft Household Waste Collection Policy which was subsequently recommended and a Waste Management Topic Group was established to scrutinise the process; · Proposed recommendations in respect of the adoption of an Abandoned Shopping Trolley Policy; · Consideration of the current practice relating to the provision of grit storage bins and manual gritting of footpaths and proposed improvements for the delivery of the service in the future. The Chairman thanked all the Councillors and Officers for their support during the year. RESOLVED: That the Annual Report be received for the purpose of its adoption at a forthcoming meeting of Full Council. |
|
Policy and Performance Board Work Programme PDF 36 KB Minutes: The Board received a report of the Strategic Director, Policy and Resources, which sought to develop a work programme of topics for the Board to examine in 2011/12. The Board had previously agreed that the Waste Management Topic Group needed to be re-established and a Topic Working Group had been set up. The Group had met on 1st June 2011 and Members received a verbal update on the work undertaken by the Topic Group to date. The Group had examined the alternative bin collection pilot schemes and the following had been noted. · The pilot scheme had been rolled out to 2,500 properties and very few issues or concerns had been reported; · More residents had been recycling as a result of the pilot; · There had been more requests for larger blue recycling bins; · Although a small number of complaints had been received, these had been prior to the introduction of the scheme and no complaints had been received since the scheme had been implemented; · It was proposed to extend the pilot into four other ward areas (Birchfield, Farnworth, Daresbury and Norton North); · Weekly bin collections would take place during the Christmas period; · The alternate bin collection scheme would not be viable for those properties with sack collections. Arising from the discussion, it was agreed that a Cemeteries Working Party be established and the Operational Director Policy, Planning and Transportation in consultation with the Chair and Vice Chair of the Environment and Urban Renewal Policy and Performance Board agree the Topic Brief. This brief was to include a timeline indicating when the Group intended to reach its conclusions by. RESOLVED: That 1) a Cemeteries Working Party be established for 2011/12 with the following Membership: Councillors Thompson (Chair), J. Bradshaw, 2) the Operational Director Policy, Planning and Transportation in consultation with the Chair and Vice Chair of the Environment and Urban Renewal Policy and Performance Board agree the Topic Brief; and
3) the Waste Management Topic Group continue as previously established. |
|
Nominations of Members to the Consultation Review Panel PDF 31 KB Minutes: The Board considered a report of the Strategic Director, Environment and Economy which requested nomination of two Members to represent the Board on the Consultation Review Panel. RESOLVED: That the Chair and Vice Chair of the Environment and Urban Renewal Policy and Performance Board sit on the Consultation Review Panel as may be required from time to time. |
|
Minutes: The Board considered a report of the Strategic Director, Environment and Economy, which requested Members to agree nominations to sit on the Council’s Public Transport Advisory Panel for the Municipal Year 2011/12. RESOLVED: That 1) the nominations for Halton Public Transport Advisory Panel for 2011/12 be as follows: Councillors Hignett, Gerrard, Stockton and Hodgkinson; 2) the key issues discussed by the Panel during the Municipal Year 2010/11 be noted.
|