Venue: Marketing Suite, Municipal Building. View directions
Contact: Lynn Derbyshire on 0151 471 7389 or e-mail lynn.derbyshire@halton.gov.uk
No. | Item |
---|---|
MINUTES Minutes: The Minutes of the meeting held on 19 November 2009 were taken as read and signed as a correct record. |
|
Additional documents: Minutes: The Board considered a report of
the Strategic Director, Environment which advised Members of the progress made towards
securing the authority required to commence the procurement process since the
last meeting of the Board in November 2009. The Board was advised that at the meeting of the last Mersey Gateway Executive
Board on 19 November, Members had been advised that the formal procurement
process for a Mersey Gateway concession contract could only commence once the
Council had secured the planning decision by the Secretaries of State and for
Ministers to grant Conditional Funding Approval. The Board was further advised that towards the end of December the
project team had contacted the Planning Inspectorate (PINS) to determine if the
report had been forwarded to the Department. The team had been advised that it
was envisaged that the Department would not receive the report until the end of
January 2010. It was reported that the Authority were optimistic that the Secretary
of State would announce a decision before a General Election in May but this
may not be the case. Consequently, the authority had raised concerns with
senior officials at the Department over the impact of such a delay and a
modified programme had been agreed based on the decision being announced by the
end of May with contingency arrangements should this not take place until later
in 2010. The Authority had also agreed the procedure for considering the
Conditional Funding Approval. This agreed procedure was reflected in the
programme set out in Appendix 1 to the report. In addition, the first draft of the Outline Business Case had been submitted
to the Department and discussed with the DfT Major
Projects Team at the progress meeting on 19 November. The key issues emerging from the progress
meeting were then considered. The main issue to be agreed with the Department
over the next few weeks was the revised procurement approach that could be
expected to secure best value from the proposed tolling regime. Options under
consideration would require the PFI Credits to be increased in return for a
greater public sector financial interest in the toll revenue which overall
could result in a better deal for the public sector. Draft proposals were due
to be put to the Department for Transport Internal Investment Committee in
February and the outcome was expected to be available and reported to members
at the next meeting of the Board in March.
RESOLVED: That (1) the progress made and the revised
outlook for commencing procurement later this year be noted; and (2) the development budget estimated
to be required to deliver the Conditional Funding submission to the Department
for Transport and to undertake all necessary preparation to enable procurement to commence as soon as
Conditional Approval is granted by Ministers be noted. |
|
SCHEDULE 12A OF THE LOCAL GOVERNMENT ACT 1972 AND THE LOCAL GOVERNMENT (ACCESS TO INFORMATION) ACT 1985 Minutes: The Board considered: (1) whether
Members of the press and public should be excluded from the meeting of the
Board during consideration of the following items of business in accordance with
Sub-Section 4 of Section 100A of the Local Government Act 1972 because it was
likely that, in view of the nature of the business to be considered, exempt
information would be disclosed, being information defined in Section 100 (1)
and paragraph 3 of Part I of Schedule 12A of the Local Government Act 1972; and (2) whether the disclosure of information was in the public
interest, whether any relevant exemptions were applicable and whether, when
applying the public interest test and exemptions, the public interest in
maintaining the exemption outweighed that in disclosing the information. RESOLVED: That as, in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information, members of the press and public be excluded from the meeting during consideration of the following items of business in accordance with Sub-Section 4 of section 100A of the Local Government Act 1972 because it is likely that, in view of the nature of the business, exempt information will be disclosed, being information defined in Section 100(1) and paragraph 3 of Part I of Schedule 12A of the Local Government Act 1972. |
|
Land Assembly Progress and Land Acquisition Capital Expenditure Budget Forecast 2010/11 Minutes: The Board considered a report of the Strategic Director, Environment which advised Members of progress to date with the advanced acquisition of land required for the Mersey Gateway in advance of CPO/TWA and the land acquisition capital expenditure requirement for 2010/11. RESOLVED: That (1)
the progress made in assembling the land required for the Mersey Gateway
be noted; and (2)
the requested land acquisition capital expenditure
budget for 2010/11 as outlined at Paragraph 3.14 of the report be approved. |